Groundwater Sensor Installation at LGU Maddela, Quirino.

On July 23, 2025, SWIM Technical staffs represented by engr. Glen Batoon, engr. Kathleen Palma, engr. Wilfredo Bose, and engr. Bermiel Allen Tuppil traveled to Maddela, Quirino to install the 7th groundwater monitoring system. The team is welcomed by Mr. Rogelio Valdez with the LGU staffs in the MPDO office and then proceed at the installation site found in the vicinity of Municipal Hall compound. The team assembled and installed the system components, which included a battery, solar panel, sensors, wiring, and protective instrument housing. Each part was carefully connected to ensure the system functioned properly and efficiently. As part of the installation process, the SWIM team also trained local personnel on how to restart the instrument in the event of a power outage. Once the setup was complete, they carried out a thorough inspection to verify that everything was operating smoothly and as intended.